Development
Location
Planning
Region
Developer
Estimated
NLA (sq m)
Hyfux Innovation
Centre
Bendemeer Road
Central
Hyfux
336,000
The Splendour
Bukit Batok Crescent
West
Sin Soon Lee
Development
334,000
A’Posh Bizhub
Yishun Industrial Street 1
North
OKH Management
290,000
9 @ Tagore
Tagore Lane
North East
Chiu Teng
270,000
Q3 2012
Single-user factory Tuas South Avenue 12
West
Halliburton
489,000
North Point Bizhub Yishun Industrial Street 1
North
Soilbuild Group Holdings
366,000
Q4 2012
Woodlands 11
Woodlands Close
North
Boon Keng Development
745,000
One@Changi City
Changi Business Park
Central 1
East
Ascendas/ Frasers
Centrepoint
651,000
Harvest @
Woodlands
Woodlands Industrial
Park E5
North
Wee Hur Holdings
626,000
Source: URA, DTZ Consulting & Research, February 2013
Private factory stock, as at end 2012, comprised approximately 28% (78.5 million sq ft) multiple-user factory
space, 68% (191.1 million sq ft) single-user factory space, and 4% (12.5 million sq ft) business park space.
3.2
Potential Supply
8
According to the Urban Redevelopment Authority (“URA”), about 51.1 million sq ft
9
of private factory space is
in the pipeline as at Q4 2012, of which about 66% (33.8 million sq ft) is under construction. Of the remaining
34% (17.3 million sq ft) that is still being planned, about half (8.5 million sq ft) has not obtained written or
provisional permission (Figure 1.3).
Figure 1.3: Pipeline Supply of Private Factory Space by Development Status
10
Source: URA, DTZ Consulting & Research, February 2013
25,000
‘000 sq ft
20,000
15,000
10,000
5,000
2013
2014
2015
2016
2017
>2017
Under Construction
Planned
8
All potential supply is in GFA.
9
Includes all private factory space in the pipeline, regardless of size or planning status.
10
Includes the supply from new development and redevelopment projects with provisional and written permission as well from other categories of supply e.g.
(i) projects with Outline Provisional Permission, (ii) developments submitted for planning approval and which are under consideration, (iii) projects on awarded
GLS sites for which plans have not been submitted for planning approval, (iv) planned projects in the Government Land Sales programme (which refer to sites
on the GLS confrmed list and sites on the GLS reserve list that have been triggered), and (v) planned public developments for which plans have not been
submitted to URA for planning approval.